![]() |
Project Risk Management |
Project risks are uncertain events or conditions that may have a positive
(Opportunity) or negative (Threat) effect on one or more project objectives
(e.g., Scope, Schedule, Cost, Quality) if occur. A risk may have one or more causes and may
have one or more impacts.
Project Risk Management is a valuable part of
project management and when performed appropriate, it enhances the complete
project management execution and its change to success.
As define by PMI, “Project Risk Management includes the processes of conducting risk
management planning, identification, analysis, response planning, and
controlling risk on a project. The
objectives of project risk management are to increase the likelihood and impact
of positive events, and decrease the likelihood and impact of negative events
in the project” (PMBOK 5thEd.)
Project Risk Management concentrates on
project’s uncertainties. Some uncertainties are known (e.g., Lessons Learned,
Historical Data) and some are unknown or emerge during project execution. For this reason risk identification should be
performed as early as possible in the project.
When performing Project Risk Management, the
following steps should be observed:
Plan Risk Management – This process defines and establishes how the
project risk management will be performed. The output is the Project Risk
Management Plan and it should be developed and approved early in the project
and should be part of the Project Management Plan.
Identify Risks - The process of identify
those risks that may affect the project and documenting their characteristics. During this process observe early risks
identification, iterative identification, emergent identification, explicit
identification of opportunities, multiple perspectives and link risks to
project objectives, complete risk statement (Scope, Schedule, Cost, Quality,
etc.). The output is the Project Risk Register. Risk Owners are preliminary assigned.
Perform Qualitative Risk Analysis – This process evaluates the characteristics of those risks previously
identified during the Identify Risk step. During this process risks are prioritized for
further analysis by assessing their probability of occurrence and impact. Categories, level of probability and impact
should be previously stated and agreed in the Project Risk Management Plan. The output is the updated Project Risk Register.
Perform Quantitative Risk Analysis – This process analyze numerically the effect of identified risks on
overall project. Using quantitative
techniques such as Monte Carlo simulation may produce a better estimate of
risks impact on schedule or cost. Not
all projects require Quantitative Risk Analysis. The Project Risk Management Plan should state
the type of risk analysis that will be performed. The output is the updated Project Risk Register.
Plan Risk Responses - The process establish
effective response actions in accordance the priority of the identified and
assessed risks, and complying with applicable organizational and project
constraints. In other words, establish actions
to enhance opportunities and to reduce threats to project objectives. The output is the updated Project Risk Register.
Control Risks – This process tracks identified risks, monitor
residual risks, identify new risks, reevaluate identified risks, continuously
monitor risks trigger conditions, maintain risks awareness, ensure response
action are performed and implemented appropriate on time as expected and
evaluate responses effectiveness throughout the project. This Control Risks should be integrated with
the Project Monitoring and Control. The
output is the updated Project Risk Register.
Perform risks assessment periodically as stated in the Project Risk
Management Plan.
As part of the Project Manager role, the following responsibilities
should be performed to enhance project risk management performance:
- Encourage senior management to support Project Risk Management process
- Promote the Project Risk Management process for the project
- Facilitate open and honest communication about project risks
- Regularly report risks status to project sponsor and key stakeholders
- Escalate identified risks to senior management when required
- Monitor risks response actions effectiveness
- Documents Project Risk Management Lessons Learned
Remember that Project Risk Management is an iterative process and should
be performed starting early in the project until project completion, including
its discussion during the Lessons Learned session.
Very well written ,I love reading your blogs as its very informative, & I found this
ReplyDeletevery informative for my study as well, I am also doing my online MBA Course in risk management from a distance learning center.